Since my last update nothing has happened ON the site.
The builder gave the framer a deadline of Wednesday the 4th to get back on the job or be replaced. They did not arrive yesterday for that deadline, so the paperwork to initiate the transition has begun. One slice of good news, the builder did send the framer they had just finish a job in Darrington job come by and access the framing here. He said given all that he needs to fix he would need to be paid as if he did the entire project. Great. I let him know I have no control over the financial part and to work that out with GC . . that is their financial mess to clean up. GC is working out a plan with the new framer and will contact me with a new timeline. They expect it to take 2 weeks to complete the framing.
Now we shift the next trades another 2 weeks for the 3rd time!
Oh and they are planning to have a Weyerhaeuser rep come out to do a quality control check on our framing since it has sat WET for so long!