Wednesday, January 20, 2021

Roofing delivery tomorrow 1/21!

 I don't count on anything the builder tells me at this point BUT we've been told the metal roof material will be here tomorrow. The roofer had told the GC they will be here Friday or Monday to install. I hope this timeline is correct as the rain is moving back in the end of next week. We are on 40 days of no activity (besides roof paper). 

Drying out well with all the dry weather


Standing in living room, looking towards kitchen/nook area

Master bath shower

Master bath tub

Kids bathroom


Framing issue in the kids bedrooms - all related to the truss correction


No comments:

Post a Comment

Cedar deck complete, tiled porch . . still in progress

 The back deck outside the 12' slider is only 4' deep to accomodate county code. We hope to add to it later when budget allows and/o...