4 weeks after the original framers went MIA, they show up to fix their mistakes. The idea of a new framer didn't come through since their schedule couldn't accommodate us before the original framer came back. I am fairly certain the framers have framed 3 other houses in the day they started our project back in August. In the end I am just glad SOMETHING is happening. Since we have had so much rain they have really tore up the beautiful dirt work we had done . . so that will need to be fixed in the spring. We should see the framing wrapped up next week. They need to set the vaulted ceiling trusses, and then sheet the roof. All other trades on hold until that work is done.
What a mess!
November 8th, 2020 First really noticeable frost:
No comments: