Thursday, December 3, 2020

Windows in, Framing 90%, plumber starting

 Today it actually feels like a jobsite. Lots happening. Project manager made and extra visit (wasn't due until next Friday), construction manager texted me for the 2nd time this week asking for pictures and keeping in touch. I asked the project manager what he did to put the flame to their feet. He said "I freaked out on them a bit". He is new to this company and position, but I am thankful for him being an advocate for us and getting things on track!

Its super frosty and icey here today, so the framers are waiting for the sun to melt the frost on the roof so they can finish sheeting. 












No comments:

Post a Comment

Cedar deck complete, tiled porch . . still in progress

 The back deck outside the 12' slider is only 4' deep to accomodate county code. We hope to add to it later when budget allows and/o...