The framers came in on 10/19 and 10/20 to start the 'fix' on the trusses. We haven't seen them back since then. They were supposed to have it fixed by Friday the 23rd. The project manager and the trade coordinator are working to get answers from the framer and plan to replace them if they are not able to complete before the plumber is scheduled on 11/9. Bad news is that in order to find a new framer it will take time therefore we would see additional delays.
So here we sit, waiting . . . with a wet soggy house :(