We passed the inspection today with the county for footing drains. Our plans show splash blocks for the downspouts, however we plan to go back later and upgrade drainage for roof/downspouts. In order to make this easier we laid some pipe to tie into later. 
We were both tired after working all day, but we jumped in and worked on the drains as well as cleaning out the crawl space. The foundation sub made a huge mess when they poured. Using a magnet tool Aleesa picked up most of the nails while I broke up the pieces of concrete and raked into a pile to later shovel outside the crawl space area. More to come tonight! Always more to do.  .







No comments:

Post a Comment

Cedar deck complete, tiled porch . . still in progress

 The back deck outside the 12' slider is only 4' deep to accomodate county code. We hope to add to it later when budget allows and/o...