We knew we wanted to have a webpage to document our home build process. It's been a long journey and one we want to be able to look back on. After the project started going downhill we realized documenting it was must.
Thursday, January 28, 2021
Friday, January 22, 2021
Metal roofing finally arrived, maybe the correct color?
One promise that ended up true . . Roofing was delivered yesterday 1/21/21!
I immediately noticed the color noted on the packing slip is different than the color we ordered. We ordered leaf green after comparing a sample to the existing building back in Nov 2019. The color here . . forest green. We are hopeful it is close enough, but seriously. This supplier has two greens, how does this happen? I did notice on the phase 1 selections sheet from GC (shown on top below), that the roof color just says 'green', however when we were given the metal sample she said it would be for roof and gutters.
Also notice on this packing slip. ORDER DATE: 1/15/21. Really? After GC SWORE it was ordered back in mid-December and the pandemic was slowing it down due to factory delays? Yeah, ok.
Wednesday, January 20, 2021
Roofing delivery tomorrow 1/21!
I don't count on anything the builder tells me at this point BUT we've been told the metal roof material will be here tomorrow. The roofer had told the GC they will be here Friday or Monday to install. I hope this timeline is correct as the rain is moving back in the end of next week. We are on 40 days of no activity (besides roof paper).
Drying out well with all the dry weather
Friday, January 8, 2021
Tarping the roof
Friday, January 1, 2021
Still waiting on metal
Roof paper went on 12/18. Now the builder says there is a delay from the factory on the roof metal, but yet cannot provide a delivery date. They cannot seem to stick to a schedule. I get that covid is causing delays, but they should be able to adjust that schedule and plan for delays. Everything has been open ended and non-committal.
Here are some pictures taken this week after the dry days turned to rain. The inside was drying really well with the fans, but then the rain and drips started. Now we are back to sweeping out water a few times a day. I did have ProServ visit on Wednesday to put together a proposal on mold mitigation.
This water is not coming in from the window
Cedar deck complete, tiled porch . . still in progress
The back deck outside the 12' slider is only 4' deep to accomodate county code. We hope to add to it later when budget allows and/o...
-
I've been doing finishing touches on tile. I still have a lot of sealing to do on the river rock and marble tile in the kitchen. Today I...
-
As part of the original septic design we knew we needed to install an additional tank closer to the house that would feed into the other tan...
-
Crazy to think we started this process back in 2015 right before Mike deployed. TIMELINE: Early 2015 - Owner contract on land : A family f...