We were told roofer was supposed to start 12/10 (that was after pushing phase 1 subs out many times due to the framing delays). That was 8 days ago now. The project manager called us Tuesday night saying he talked to the roofer and was told he would be out this week to at least paper the roof. The metal next week. I wrote GC Monday night expressing my dissatisfaction with the newest delays. Apparently the roofer did get 4 calls from GC staff regarding our project on Tuesday, but no management ever contacted us to say they were working on it. We have been running fans for a week now, but the rain keeps getting in due to the access panel and the open ridge caps. Hopefully we see him today?
A few recent photos:
From the loft looking down into the dining/living area
Woodstove vent, can't wait for the wood heat!
All the windows looking out the back yard! 12' slider will be nice in the summer too.
Kids rooms have closets. This was the last framing items to be done . .
they claimed their plans didn't show closets? Really?
Weird corner wall where they had to run a large pipe down. Mike hate angled walls.
Hard to see here . . but the snow is getting closer!