We knew we wanted to have a webpage to document our home build process. It's been a long journey and one we want to be able to look back on. After the project started going downhill we realized documenting it was must.
Wednesday, October 14, 2020
Kids pose in their new rooms
Friday, October 9, 2020
Some framing progress
Windows were delivered on Monday the 5th (double slider on back order, coming the 12th). The framing crew brought a 4th guy Thursday this week. They were able to get the large trusses set. Earlier in the week they install the 5 small front windows, built the stair landings and installed the porch posts and beams. Supposed to get rain tonight, still no sheeting or roof.
Friday, October 2, 2020
Where did the framers go??
The trusses were delivered almost 2 weeks ago on Monday the 21st. We saw the framers working on the 22nd. The 23rd the rain moved in and they picked up their tool trailer and left. I've been trying to get an update from our project manager since then (who says he is trying to reach the framer/sub). The construction manager called me yesterday after I sent and email concerned about this delay. He said it likely due to weather. REALLY!? It's been sunny for the past 5-6 days! We did have rain the 23rd-26th, and dealt with the water on our own after the builder didn't return calls/text. There is no reason for no progress this week. Very frustrating to not have a roof on yet.
Dealing with water for a few days while Mike was gone. Xander is great helping me:
Cabinet colors
Monday, September 21, 2020
Truss day!
September 21, 2020 - Trusses today. 6 days later than originally planned.
Next - woodstove venting 9/30, then roof and windows! Lets hope the heavy rains hold off a but longer...we've already had 2 good storms pour down on us before roofing.
Friday, September 11, 2020
Monday, September 7, 2020
Cedar deck complete, tiled porch . . still in progress
The back deck outside the 12' slider is only 4' deep to accomodate county code. We hope to add to it later when budget allows and/o...
-
With how our project has drug out so long, we have had plenty of time to agonize over colors and materials. This week we had to finalize fl...
-
On the day after Thanksgiving I am thankful we have a project manager that visited on his day off and actually seems to give a crap about th...
-
Today 9/7 the framers erected the first walls! Aleesa looking out back at the nook area ...